    162-H:10 Public Hearing; Studies; Rules. –
I. At least 30 days prior to filing an application for a certificate, an applicant shall hold at least one public information session in each county where the proposed facility is to be located and shall, at a minimum, publish a public notice not less than 14 days before such session in one or more newspapers having a regular circulation in the county in which the session is to be held, describing the nature and location of the proposed facility. The applicant shall also send a copy of the public notice, not less than 14 days before the session, by first class mail to the governing body of each affected municipality. At such session, the applicant shall present information regarding the project and provide an opportunity for comments and questions from the public to be addressed by the applicant. Not less than 10 days before such session, the applicant shall provide a copy of the public notice to the chairperson of the committee. The applicant shall arrange for a transcript of such session to be prepared and shall include the transcript in its application for a certificate.
I-a. Within 45 days after acceptance of an application for a certificate, pursuant to RSA 162-H:7, the applicant shall hold at least one public information session as described in paragraph I in each county in which the proposed facility is to be located and shall, at a minimum, publish a public notice not less than 14 days before said session in one or more newspapers having a regular circulation in the county in which the session is to be held, describing the nature and location of the proposed facility. The applicant shall also send a copy of the public notice, not less than 14 days before the session, by first class mail to the governing body of each affected municipality. Not less than 10 days before such session, the applicant shall provide a copy of the public notice to the presiding officer of the committee. The administrator, or a designee of the presiding officer of the committee, shall act as presiding officer of the information session. The session shall be for public information on the proposed facility with the applicant presenting the information to the public. The presiding officer shall also explain to the public the process the committee will use to review the application for the proposed facility.
I-b. Upon request of the governing body of a municipality or unincorporated place in which any part of the proposed facility is to be located, or on the committee's own motion, the committee may order the applicant to provide such additional public information sessions as described in paragraph I as are reasonable to inform the public of the proposed project.
I-c. Within 90 days after acceptance of an application for a certificate, pursuant to RSA 162-H:7, the site evaluation committee shall hold at least one public hearing in each county in which the proposed facility is to be located and the applicant shall publish a public notice not less than 14 days before such hearing in one or more newspapers having a regular circulation in the county in which the hearing is to be held, describing the nature and location of the proposed facilities. Not fewer than 10 days before such session, the applicant shall provide a copy of the public notice to the presiding officer of the committee. The applicant shall arrange for a transcript of such session to be prepared. Except for state agencies and programs that are required by state or federal law or regulation to comply with program specific public notice and public hearing requirements, the public hearings may be joint hearings, with representatives of the agencies that have permitting or other regulatory authority over the subject matter and shall be deemed to satisfy all initial requirements for public hearings under statutes requiring permits relative to environmental impact. The hearing may be a joint hearing with the other state agencies; provided, however, if any of such other state agencies does not otherwise have authority to conduct hearings, it may not join in the hearing under this chapter; provided further, however, the ability or inability of any of the other state agencies to join shall not affect the composition of the committee under RSA 162-H:3 nor the ability of any member of the committee to act in accordance with this chapter.
II. Subsequent public hearings shall be in the nature of adjudicative proceedings under RSA 541-A and shall be held in the county or one of the counties in which the proposed facility is to be located or in Concord, New Hampshire, as determined by the site evaluation committee. The committee shall give adequate public notice of the time and place of each subsequent hearing.
III. The site evaluation committee shall consider and weigh all evidence presented at public hearings and shall consider and weigh written information and reports submitted to it by members of the public before, during, and subsequent to public hearings but prior to the closing of the record of the proceeding. The committee shall provide an opportunity at one or more public hearings for comments from the governing body of each affected municipality and residents of each affected municipality. The committee shall consider, as appropriate, prior committee findings and rulings on the same or similar subject matters, but shall not be bound thereby.
IV. The site evaluation committee shall require from the applicant whatever information it deems necessary to assist in the conduct of the hearings, and any investigation or studies it may undertake, and in the determination of the terms and conditions of any certificate under consideration.
V. The site evaluation committee and counsel for the public shall conduct such reasonable studies and investigations as they deem necessary or appropriate to carry out the purposes of this chapter and may employ a consultant or consultants, legal counsel and other staff in furtherance of the duties imposed by this chapter, the cost of which shall be borne by the applicant or certificate holder in such amount as may be approved by the committee. The site evaluation committee and counsel for the public are further authorized to assess the applicant or certificate holder for all travel and related expenses associated with the processing of an application or other proceedings under this chapter.
VI. The site evaluation committee shall issue such rules to administer this chapter, pursuant to RSA 541-A, after public notice and hearing, as may from time to time be required.
VII. As soon as practicable but no later than November 1, 2015, the committee shall adopt rules, pursuant to RSA 541-A, relative to the organization, practices, and procedures of the committee and criteria for the siting of energy facilities, including specific criteria to be applied in determining if the requirements of RSA 162-H:16, IV have been met by the applicant for a certificate of site and facility. Prior to the adoption of such rules, the department of energy shall hire and manage one or more consultants to conduct a public stakeholder process to develop recommended regulatory criteria, which may include consideration of issues identified in attachment C of the 2008 final report of the state energy policy commission, as well as others that may be identified during the stakeholder process. Except for the cases where the adjudicatory hearing has commenced, applications pending on the date rules adopted under this paragraph take effect shall be subject to such rules. Prior to the adoption of rules under this paragraph, applications shall be continuously processed pursuant to the rules in effect upon the date of filing. If the rules require the submission of additional information by an applicant, such applicant shall be afforded a reasonable opportunity to provide that information while the processing of the application continues.

Source. 1991, 295:1. 1997, 298:27. 2007, 364:7. 2009, 65:14. 2013, 134:2, eff. June 26, 2013. 2014, 217:16, eff. July 1, 2014. 2015, 219:11, eff. July 8, 2015; 268:3, eff. July 20, 2015. 2017, 115:3, 4, eff. Aug. 14, 2017; 156:64, eff. July 1, 2017. 2018, 216:4, eff. Aug. 7, 2018. 2021, 91:200, eff. July 1, 2021. 2022, 176:7, eff. Aug. 6, 2022. 2023, 233:11, eff. Oct. 7, 2023.