TITLE XII
PUBLIC SAFETY AND WELFARE
CHAPTER 162-H
ENERGY FACILITY EVALUATION, SITING, CONSTRUCTION AND OPERATION
Section 162-H:1
162-H:1 Declaration of Purpose.
The legislature recognizes that the selection of sites for energy facilities, including the routing of high voltage transmission lines and energy transmission pipelines, will have a significant impact upon the welfare of the population, the location and growth of industry, the overall economic growth of the state, the environment of the state, and the use of natural resources. Accordingly, the legislature finds that it is in the public interest to maintain a balance between the environment and the need for new energy facilities in New Hampshire; that undue delay in the construction of needed facilities be avoided and that full and timely consideration of environmental consequences be provided; that all entities planning to construct facilities in the state be required to provide full and complete disclosure to the public of such plans; and that the state ensure that the construction and operation of energy facilities is treated as a significant aspect of land-use planning in which all environmental, economic, and technical issues are resolved in an integrated fashion, all to assure that the state has an adequate and reliable supply of energy in conformance with sound environmental principles. The legislature, therefore, hereby establishes a procedure for the review, approval, monitoring, and enforcement of compliance in the planning, siting, construction, and operation of energy facilities.
Source. 1991, 295:1. 1998, 264:1, eff. June 26, 1998. 2009, 65:1, eff. Aug. 8, 2009.
Section 162-H:2
162-H:2 Definitions.
   
I. ""Acceptance'' means a determination by the committee that it finds that the application is complete and ready for consideration.
   
II. [Repealed.]
   
II-a. ""Certificate'' or ""certificate of site and facility'' means the document issued by the committee, containing such terms and conditions as the committee deems appropriate, that authorizes the applicant to proceed with the proposed site and facility.
   
III. ""Commencement of construction'' means any clearing of the land, excavation or other substantial action that would adversely affect the natural environment of the site of the proposed facility, but does not include land surveying, optioning or acquiring land or rights in land, changes desirable for temporary use of the land for public recreational uses, or necessary borings to determine foundation conditions, or other preconstruction monitoring to establish background information related to the suitability of the site or to the protection of environmental use and values.
   
IV. [Repealed.]
   
V. ""Committee'' means the site evaluation committee established by this chapter.
   
VI. ""Energy'' means power, including mechanical power or useful heat, derived from any resource, including, but not limited to, oil, coal, and gas.
   
VII. ""Energy facility'' means:
      
(a) Any industrial structure that may be used substantially to extract, produce, manufacture, transport or refine sources of energy, including ancillary facilities as may be used or useful in transporting, storing or otherwise providing for the raw materials or products of any such industrial structure. This shall include but not be limited to industrial structures such as oil refineries, gas plants, equipment and associated facilities designed to use any, or a combination of, natural gas, propane gas and liquefied natural gas, which store on site a quantity to provide 7 days of continuous operation at a rate equivalent to the energy requirements of a 30 megawatt electric generating station and its associated facilities, plants for coal conversion, onshore and offshore loading and unloading facilities for energy sources and energy transmission pipelines that are not considered part of a local distribution network.
      
(b) Electric generating station equipment and associated facilities designed for, or capable of, operation at any capacity of 30 megawatts or more.
      
(c) An electric transmission line of design rating of 100 kilovolts or more, associated with a generating facility under subparagraph (b), over a route not already occupied by a transmission line or lines.
      
(d) An electric transmission line of a design rating in excess of 100 kilovolts that is in excess of 10 miles in length, over a route not already occupied by a transmission line.
      
(e) A new electric transmission line of design rating in excess of 200 kilovolts.
      
(f) A renewable energy facility.
      
(g) Any other facility and associated equipment that the committee determines requires a certificate, consistent with the findings and purposes of RSA 162-H:1, either on its own motion or by petition of the applicant or 2 or more petitioners as defined in RSA 162-H:2, XI.
   
VIII. ""Filing'' means the date on which the application is first submitted to the committee.
   
IX. ""Person'' means any individual, group, firm, partnership, corporation, cooperative, municipality, political subdivision, government agency or other organization.
   
X. [Repealed.]
   
X-a. [Repealed.]
   
XI. ""Petitioner'' means a person filing a petition meeting any of the following conditions:
      
(a) A petition endorsed by 100 or more registered voters in the host community or host communities.
      
(b) A petition endorsed by 100 or more registered voters from abutting communities.
      
(c) A petition endorsed by the governing body of the host community or 2 or more governing bodies of abutting communities.
      
(d) A petition filed by the potential applicant.
   
XII. ""Renewable energy facility'' means electric generating station equipment and associated facilities designed for, or capable of, operation at a nameplate capacity of greater than 30 megawatts but less than 120 megawatts and powered by wind energy, geothermal energy, hydrogen derived from biomass fuels or methane gas, ocean thermal, wave, current, or tidal energy, methane gas, biomass technologies, solar technologies, or hydroelectric energy. ""Renewable energy facility'' shall also include electric generating station equipment and associated facilities of 30 megawatts or less nameplate capacity but at least 5 megawatts which the committee determines requires a certificate, consistent with the findings and purposes set forth in RSA 162-H:1, either on its own motion or by petition of the applicant or 2 or more petitioners as defined in RSA 162-H:2, XI.
Source. 1991, 295:1. 1997, 298:21-24. 1998, 264:2, eff. June 26, 1998. 2007, 25:1, eff. May 11, 2007; 364:3. eff. July 17, 2007. 2008, 348:8, eff. July 7, 2008. 2009, 65:2-4, 24, I-IV, eff. Aug. 8, 2009.
Section 162-H:3
162-H:3 Site Evaluation Committee.
The site evaluation committee shall consist of the commissioner of the department of environmental services or assistant commissioner as designee, the director of the division of water, the commissioner of the department of resources and economic development or the director of the division of economic development as designee, the commissioner of the department of health and human services or one of the 2 most senior administrators within the department responsible for management of public health services as designee, the executive director of the fish and game department, the director of the office of energy and planning or deputy director as designee, the director of the division of parks and recreation, the director of the division of forests and lands, the director of the division of air resources, the commissioner of the department of transportation or assistant commissioner as designee, the commissioners of the public utilities commission, a staff engineer designated by the commissioners of the public utilities commission, and the commissioner of the department of cultural resources or director of the division of historical resources as designee. The commissioner of the department of environmental services shall be chairperson of the committee, and the chairperson of the public utilities commission shall be vice-chairperson.
Source. 1991, 295:1. 1995, 310:182. 1996, 228:41. 1997, 298:25, eff. June 20, 1997. 2002, 247:2, eff. July 16, 2002. 2003, 319:9, eff. July 1, 2003. 2004, 257:44, eff. July 1, 2004. 2007, 364:4, eff. July 17, 2007. 2009, 65:5, eff. Aug. 8, 2009.
Section 162-H:4
162-H:4 Powers of the Committee.
   
I. The committee shall:
      
(a) Issue any certificate under this chapter for an energy facility.
      
(b) Determine the terms and conditions of any certificate issued under this chapter.
      
(c) Monitor the construction and operation of any energy facility granted a certificate under this chapter.
      
(d) Enforce the terms and conditions of any certificate issued under this chapter.
   
II. The committee shall hold hearings as required by this chapter and such additional hearings as it deems necessary and appropriate.
   
III. The committee may delegate the authority to monitor the construction or operation of any energy facility granted a certificate under this chapter to such state agency or official represented on the committee as it deems appropriate, but, subject to RSA 162-H:10, it may not delegate authority to hold hearings, issue certificates, determine the terms and conditions of a certificate, or enforce a certificate. Any authorized representative or delegate of the committee shall have a right of entry onto the premises of any part of the energy facility to ascertain if the facility is being constructed or operated in continuing compliance with the terms and conditions of the certificate. During normal hours of business administration and on the premises of the facility, such a representative or delegate shall also have a right to inspect such records of the certificate-holder as are relevant to the terms or conditions of the certificate.
   
III-a. The committee may delegate to an agency or official represented on the committee the authority to specify the use of any technique, methodology, practice, or procedure approved by the committee within a certificate issued under this chapter, or the authority to specify minor changes in the route alignment to the extent that such changes are authorized by the certificate for those portions of a proposed electric transmission line or energy transmission pipeline for which information was unavailable due to conditions which could not have been reasonably anticipated prior to the issuance of the certificate.
   
IV. In cases where the committee determines that other existing statutes provide adequate protection of the objectives of RSA 162-H:1, the committee may, within 60 days of acceptance of the application, or filing of a request for exemption with sufficient information to enable the committee to determine whether the proposal meets the requirements set forth below, and after holding a public informational hearing in a county where the energy facility is proposed, exempt the applicant from the approval and certificate provisions of this chapter, provided that the following requirements are met:
      
(a) Existing state or federal statutes, state or federal agency rules or municipal ordinances provide adequate protection of the objectives of RSA 162-H:1;
      
(b) A review of the application or request for exemption reveals that consideration of the proposal by only selected agencies represented on the committee is required and that the objectives of RSA 162-H:1 can be met by those agencies without exercising the provisions of RSA 162-H;
      
(c) Response to the application or request for exemption from the general public indicates that the objectives of RSA 162-H:1 are met through the individual review processes of the participating agencies; and
      
(d) All environmental impacts or effects are adequately regulated by other federal, state, or local statutes, rules, or ordinances.
   
V. Once an energy facility application has been accepted, the chairperson may designate a subcommittee of no fewer than 7 members that shall consider such application. The subcommittee shall include the chairperson or the vice-chairperson of the committee, and at least 3 members selected from among the department of environmental services, the department of resources and economic development, and the fish and game department. With the exception of the chairperson or vice-chairperson, each member of the committee may designate an employee from his or her agency to assume his or her responsibilities as a subcommittee member for the purposes of this paragraph, provided that such designee shall be a senior administrator within the agency, department, or division that the member represents under RSA 162-H:3. The chairperson may designate the assistant commissioner of the department of environmental services to assume his or her responsibilities as a subcommittee member for the purposes of this paragraph. For purposes of statutory interpretation and executing the regulatory functions of this chapter, the subcommittee shall assume the role of and be considered the committee, with all of its associated powers and duties.
Source. 1991, 295:1. 1997, 298:26, eff. June 20, 1997. 2007, 364:5, eff. July 17, 2007. 2008, 348:7, eff. July 7, 2008. 2009, 65:6-8, eff. Aug. 8, 2009.
Section 162-H:5
162-H:5 Prohibitions and Restrictions.
   
I. No person shall commence to construct any energy facility within the state unless it has obtained a certificate pursuant to this chapter. Such facilities shall be constructed, operated and maintained in accordance with the terms of the certificate. Such certificates are required for sizeable changes or additions to existing facilities. Such a certificate shall not be transferred or assigned without approval of the committee.
   
II. Facilities certified pursuant to RSA 162-F or RSA 162-H prior to January 1, 1992, shall be subject to the provisions of those chapters; however, sizable changes or additions to such facilities shall be certified pursuant to this chapter.
   
III. The applications shall be governed by the applicable laws, rules and regulations of the agencies and shall be subject to the provisions of RSA 162-F or RSA 162-H in effect on the date of filing. Notwithstanding the foregoing, an applicant may request the site evaluation committee to assume jurisdiction and in the event that the site evaluation committee agrees to assert jurisdiction, the facility shall be subject to the provisions of this chapter.
   
IV. [Repealed.]
Source. 1991, 295:1. 1998, 264:3, eff. June 26, 1998. 2009, 65:9, 24, V, eff. Aug. 8, 2009.
Section 162-H:6
162-H:6 Time Frames.
[Repealed 2009, 65:24, VI, eff. Aug. 8, 2009.]
Section 162-H:6-a
162-H:6-a Time Frames for Review of Renewable Energy Facilities.
   
I. Upon the filing of an application for a certificate for a renewable energy facility, the chairperson shall expeditiously forward to each of the other state agencies having jurisdiction, under state or federal law, to regulate the construction or operation of the proposed facility, a copy of the parts of the application that are relevant to its jurisdiction. Upon the filing of the copy, each of the other state agencies shall conduct a preliminary review as described in RSA 162-H:7, IV. To qualify for the time frames for review specified in this section, an application for a renewable energy facility shall include testimony, exhibits, and sufficient information to satisfy the application requirements of each state agency having jurisdiction, under state or federal law, to regulate the construction or operation of the proposed facility, and shall include each agency's completed application forms.
   
II. Upon the filing of an application for a certificate for a renewable energy facility, the chairperson or designee shall expeditiously conduct a preliminary review to ascertain whether the application contains sufficient information to carry out the purposes of this chapter. The chairperson or designee shall require as much information as he or she deems necessary to review the application and may take other administrative or procedural actions on behalf of the committee to aid in the orderly conduct of the proceeding.
   
III. The chairperson of the committee or designee shall decide whether or not to accept the application within 30 days of filing. Once an application has been accepted the chairperson shall designate a subcommittee as provided in RSA 162-H:4, V.
   
IV. After acceptance of the application, the subcommittee, upon 30 days notice, shall promptly hold at least one public hearing in each county in which the proposed facility is to be located.
   
V. All participating state agencies shall report their progress to the subcommittee within 90 days of the acceptance of the application, outlining draft permit conditions and specifying additional data requirements necessary to make a final decision.
   
VI. All participating state agencies shall make and submit to the subcommittee a final decision on the parts of the application that relate to its jurisdiction, no later than 180 days after the application has been accepted.
   
VII. Within 30 days of the submission of final decisions under paragraph VI, the subcommittee shall hold a public hearing on the merits of the application, which shall be part of an adjudicative proceeding as provided under RSA 162-H:10, II. At such public hearing, the subcommittee shall hear testimony and receive evidence submitted on behalf of the applicant, any intervenors, agencies with jurisdiction, and members of the public represented by counsel for the public appointed under RSA 162-H:9. At such public hearing the subcommittee may also receive comment from any member of the public on the application.
   
VIII. Within 240 days of the acceptance of an application, the subcommittee shall issue or deny a certificate for a renewable energy facility.
   
IX. If the subcommittee at any time during its deliberations relative to an application for a certificate deems it to be in the public interest, it may temporarily suspend its deliberations and enlarge the time frame established under this section to issue or deny a certificate.
   
X. The provisions of this section shall take precedence over any other provision of this chapter if there is a conflict.
Source. 2007, 364:6, eff. July 17, 2007. 2009, 65:10, eff. Aug. 8, 2009.
Section 162-H:7
162-H:7 Application for Certificate.
   
I. [Repealed.]
   
II. All applications for a certificate for an energy facility shall be filed with the chairman of the site evaluation committee.
   
III. Upon filing of an application, the committee shall expeditiously conduct a preliminary review to ascertain if the application contains sufficient information to carry out the purposes of this chapter. If the application does not contain such sufficient information, the committee shall, in writing, expeditiously notify the applicant of that fact and specify what information the applicant must supply.
   
IV. Each application shall contain sufficient information to satisfy the application requirements of each state agency having jurisdiction, under state or federal law, to regulate any aspect of the construction or operation of the proposed facility, and shall include each agency's completed application forms. Upon the filing of an application, the committee shall expeditiously forward a copy to the state agencies having jurisdiction. Upon receipt of a copy, each agency shall conduct a preliminary review to ascertain if the application contains sufficient information for its purposes. If the application does not contain sufficient information for the purposes of any of the state agencies having jurisdiction, that agency shall, in writing, notify the committee of that fact and specify what information the applicant must supply; thereupon the committee shall provide the applicant with a copy of such notification and specification. Notwithstanding any other provision of law, for purposes of the time limitations imposed by this section, any application made under this section shall be deemed not accepted either by the committee or by any of the state agencies having jurisdiction if the applicant is seasonably notified that it has not supplied sufficient information for any of the state agencies having jurisdiction in accordance with this paragraph.
   
V. Each application shall also:
      
(a) Describe in reasonable detail the type and size of each major part of the proposed facility.
      
(b) Identify both the preferred choice and any other choices for the site of each major part of the proposed facility.
      
(c) Describe in reasonable detail the impact of each major part of the proposed facility on the environment for each site proposed.
      
(d) Describe in reasonable detail the applicant's proposals for studying and solving environmental problems.
      
(e) Describe in reasonable detail the applicant's financial, technical, and managerial capability for construction and operation of the proposed facility.
      
(f) Document that written notification of the proposed project, including appropriate copies of the application, has been given to the appropriate governing body of each community in which the facility is proposed to be located.
      
(g) Provide such additional information as the committee may require to carry out the purposes of this chapter.
   
VI. The committee shall decide whether or not to accept the application within 60 days of filing. If the committee rejects an application because it determines it to be administratively incomplete, the applicant may choose to file a new and more complete application or cure the defects in the rejected application within 10 days of receipt of notification of rejection.
   
VI-a. Within 30 days after acceptance of the application, the committee shall hold at least one public hearing in each county in which the proposed facility is to be located, in accordance with RSA 162-H:10.
   
VI-b. All participating state agencies shall report their progress to the committee within 5 months of the acceptance of the application, outlining draft permit conditions and specifying additional data requirements necessary to make a final decision.
   
VI-c. All participating state agencies shall make and submit to the committee a final decision on the parts of the application that relate to its jurisdiction, no later than 8 months after the application has been accepted.
   
VI-d. Within 9 months of the acceptance of an application, the committee shall issue or deny a certificate for an energy facility.
   
VI-e. Notwithstanding any other provision of this chapter, the committee shall employ the time frames specified under RSA 162-H:6-a to any proposal for the upgrade of the transmission system considered part of the Coos county loop.
   
VII. Notwithstanding any other provision of law, the application shall be in lieu of separate applications that may be required by any other state agencies.
   
VIII. This chapter shall not preclude an agency from imposing its usual statutory fees.
   
IX. The applicant shall immediately inform the committee of any substantive modification to its application.
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:11-13, 24, VII, eff. Aug. 8, 2009.
Section 162-H:8
162-H:8 Disclosure of Ownership.
Any application for a certificate shall be signed and sworn to by the person or executive officer of the association or corporation making such application and shall contain the following information:
   
I. Full name and address of the person, association, or corporation.
   
II. If an association, the names and residences of the members of the association.
   
III. If a corporation, the name of the state under which it is incorporated with its principal place of business and the names and addresses of its directors, officers and stockholders.
   
IV. The location or locations where an applicant is to conduct its business.
   
V. A statement of assets and liabilities of the applicant and other relevant financial information of such applicant.
Source. 1991, 295:1, eff. Jan. 1, 1992.
Section 162-H:9
162-H:9 Counsel for the Public.
   
I. Upon notification that an application for a certificate has been filed with the committee in accordance with RSA 162-H:7, the attorney general shall appoint an assistant attorney general as a counsel for the public. The counsel shall represent the public in seeking to protect the quality of the environment and in seeking to assure an adequate supply of energy. The counsel shall be accorded all the rights and privileges, and responsibilities of an attorney representing a party in formal action and shall serve until the decision to issue or deny a certificate is final.
   
II. This section shall not be construed to prevent any person from being heard or represented by counsel; provided, however, the committee may compel consolidation of representation for such persons as have, in the committee's reasonable judgment, substantially identical interests.
Source. 1991, 295:1, eff. Jan. 1, 1992.
Section 162-H:10
162-H:10 Public Hearing; Studies; Rules.
   
I. Within 30 days after acceptance of an application for a certificate of site and facility, pursuant to RSA 162-H:7, the site evaluation committee shall hold at least one joint public hearing in each county in which the proposed facility is to be located and shall publish a public notice not less than 14 days before said hearing in one or more newspapers having a regular circulation in the county in which the hearing is to be held, describing the nature and location of the proposed facilities. The public hearings shall be joint hearings, with representatives of the other agencies that have jurisdiction over the subject matter and shall be deemed to satisfy all initial requirements for public hearings under statutes requiring permits relative to environmental impact. The hearings shall be for public information on the proposed facilities with the applicant presenting the information to the site evaluation committee and to the public. Notwithstanding any other provision of law, the hearing shall be a joint hearing with the other state agencies and shall be in lieu of all hearings otherwise required by any of the other state agencies; provided, however, if any of such other state agencies does not otherwise have authority to conduct hearings, it may not join in the hearing under this chapter; provided further, however, the ability or inability of any of the other state agencies to join shall not affect the composition of the committee under RSA 162-H:3 nor the ability of any member of the committee to act in accordance with this chapter.
   
II. Except for informational hearings, subsequent hearings shall be in the nature of adjudicative proceedings under RSA 541-A and may be held in the county or one of the counties in which the proposed facility is to be located or in Concord, New Hampshire, as determined by the site evaluation committee. The committee shall give adequate public notice of the time and place of each subsequent session.
   
III. The site evaluation committee shall consider and weigh all evidence presented at public hearings and shall consider and weigh written information and reports submitted to it by members of the public before, during, and subsequent to public hearings. The committee shall grant free access to records and reports in its files to members of the public during normal working hours and shall permit copies of such records and reports to be made by interested members of the public at their expense.
   
IV. The site evaluation committee shall require from the applicant whatever information it deems necessary to assist in the conduct of the hearings, and any investigation or studies it may undertake, and in the determination of the terms and conditions of any certificate under consideration.
   
V. The site evaluation committee and counsel for the public shall jointly conduct such reasonable studies and investigations as they deem necessary or appropriate to carry out the purposes of this chapter and may employ a consultant or consultants, legal counsel and other staff in furtherance of the duties imposed by this chapter, the cost of which shall be borne by the applicant in such amount as may be approved by the committee. The site evaluation committee and counsel for the public are further authorized to assess the applicant for all travel and related expenses associated with the processing of an application under this chapter.
   
VI. The site evaluation committee shall issue such rules to administer this chapter, pursuant to RSA 541-A, after public notice and hearing, as may from time to time be required.
Source. 1991, 295:1. 1997, 298:27, eff. June 20, 1997. 2007, 364:7, eff. July 17, 2007. 2009, 65:14, eff. Aug. 8, 2009.
Section 162-H:11
162-H:11 Judicial Review.
Decisions made pursuant to this chapter shall be reviewable in accordance with RSA 541.
Source. 1991, 295:1, eff. Jan. 1, 1992.
Section 162-H:12
162-H:12 Enforcement.
   
I. Whenever the committee determines that any term or condition of any certificate issued under this chapter is being violated, it shall, in writing, notify the person holding the certificate of the specific violation and order the person to immediately terminate the violation. If, 15 days after receipt of the order, the person has failed or neglected to terminate the violation, the committee may suspend the person's certificate. Except for emergencies, prior to any suspension, the committee shall give written notice of its consideration of suspension and of its reasons therefor and shall provide opportunity for a prompt hearing.
   
II. The committee may suspend a person's certificate if the committee determines that the person has made a material misrepresentation in the application or, in the supplemental or additional statements of fact or studies required of the applicant, or if the committee determines that the person has violated the provisions of this chapter or any rule adopted under this chapter. Except for emergencies, prior to any suspension, the committee shall give written notice of its consideration of suspension and of its reasons therefor and shall provide an opportunity for a prompt hearing.
   
III. The committee may revoke any certificate that is suspended after the person holding the suspended certificate has been given at least 90 days' written notice of the committee's consideration of revocation and of its reasons therefor and has been provided an opportunity for a full hearing.
   
IV. Notwithstanding any other provision of this chapter, each of the other state agencies having jurisdiction shall retain all of its powers and duties of enforcement.
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:15, eff. Aug. 8, 2009.
Section 162-H:13
162-H:13 Records.
Complete verbatim records shall be kept by the committee of all hearings, and records of all other actions, proceedings and correspondence of the committee shall be maintained, all of which records shall be open to the public inspection as provided for under RSA 91-A.
Source. 1991, 295:1, eff. Jan. 1, 1992.
Section 162-H:14
162-H:14 Temporary Suspension of Deliberations.
   
I. If the site evaluation committee at any time during its deliberations relative to an application for a certificate deems it to be in the public interest, it may temporarily suspend its deliberations and time frame established under RSA 162-H:7.
   
II. [Repealed.]
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:16, 24, VIII, eff. Aug. 8, 2009.
Section 162-H:15
162-H:15 Informational Meetings.
Upon request of the governing body of a community in which the proposed facility is to be located, or upon request of the committee, the applicant shall provide informational meetings to inform the public of the proposed project.
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:17, eff. Aug. 8, 2009.
Section 162-H:16
162-H:16 Findings and Certificate Issuance.
   
I. The committee shall incorporate in any certificate such terms and conditions as may be specified to the committee by any of the other state agencies having jurisdiction, under state or federal law, to regulate any aspect of the construction or operation of the proposed facility; provided, however, the committee shall not issue any certificate under this chapter if any of the other state agencies denies authorization for the proposed activity over which it has jurisdiction. The denial of any such authorization shall be based on the record and explained in reasonable detail by the denying agency.
   
II. Any certificate issued by the site evaluation committee shall be based on the record. The decision to issue a certificate in its final form or to deny an application once it has been accepted shall be made by a majority of the full membership. A certificate shall be conclusive on all questions of siting, land use, air and water quality.
   
III. The committee may consult with interested regional agencies and agencies of border states in the consideration of certificates.
   
IV. The site evaluation committee, after having considered available alternatives and fully reviewed the environmental impact of the site or route, and other relevant factors bearing on whether the objectives of this chapter would be best served by the issuance of the certificate, must find that the site and facility:
      
(a) Applicant has adequate financial, technical, and managerial capability to assure construction and operation of the facility in continuing compliance with the terms and conditions of the certificate.
      
(b) Will not unduly interfere with the orderly development of the region with due consideration having been given to the views of municipal and regional planning commissions and municipal governing bodies.
      
(c) Will not have an unreasonable adverse effect on aesthetics, historic sites, air and water quality, the natural environment, and public health and safety.
      
(d) [Repealed.]
   
V. [Repealed.]
   
VI. A certificate of site and facility may contain such reasonable terms and conditions as the committee deems necessary and may provide for such reasonable monitoring procedures as may be necessary. Such certificates, when issued, shall be final and subject only to judicial review.
   
VII. The committee may condition the certificate upon the results of required federal and state agency studies whose study period exceeds the application period.
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:18-21, 24, IX, eff. Aug. 8, 2009.
Section 162-H:17
162-H:17 Bulk Power Facility Plans.
[Repealed 2009, 65:24, X, eff. Aug. 8, 2009.]
Section 162-H:18
162-H:18 Review; Hearing.
[Repealed 2009, 65:24, XI, eff. Aug. 8, 2009.]
Section 162-H:19
162-H:19 Penalties.
   
I. The superior court, in term time or in vacation, may enjoin any act in violation of this chapter.
   
II. Any construction or operation of energy facilities in violation of this chapter, or in material violation of the terms and conditions of a certificate issued under this chapter, may result in an assessment by the superior court of civil damages not to exceed $10,000 for each day in violation.
   
III. Whoever commits any willful violation of any provision of this chapter shall be guilty of a misdemeanor if a natural person, or guilty of a felony if any other person.
Source. 1991, 295:1, eff. Jan. 1, 1992. 2009, 65:22, eff. Aug. 8, 2009.
Section 162-H:20
162-H:20 Severability.
If any provision of this chapter, or application thereof to any person or circumstance is held invalid, the invalidity does not affect other provisions or applications of the chapter which can be given effect without the invalid provisions or applications, and to this end, the provisions of this chapter are severable.
Source. 1991, 295:1, eff. Jan. 1, 1992.