CHAPTER
Env-Sw 1300
PUBLIC GRANTS FOR LANDFILL AND INCINERATOR CLOSURE
Statutory Authority: RSA 149-M:7, RSA 149-M:9, RSA 149-M:41-50
Revision Note:
Document #8459, effective 10-28-05, readopted with
amendments, renumbered, and redesignated former
Chapter Env-Wm 3000 as Env-Sw
1300, pursuant to a rules reorganization plan for Department rules approved by
the Director of the Office of Legislative Services on 9-7-05. The source notes for each section of Env-Sw 1300 identify the former subtitle Env-Wm and number for the respective rule prior to Document
#8459.
PART
Env-Sw 1301
PURPOSE AND APPLICABILITY
Env-Sw
1301.01 Purpose. The purpose of the rules in this chapter is
to:
(a)
Implement RSA 149-M:41-50, which authorizes state grants to
municipalities to encourage and assist them in closing unlined solid waste
landfills and certain municipal incinerators; and
(b)
Supplement RSA 149-M:41-50.
Source. #6095, eff 9-26-95;
ss by #7492, eff 5-18-01;
(See Revision Note at chapter heading for Env-Sw
1300); ss by #8459, eff 10-28-05 (formerly Env-Wm 3001.01); ss by #10599,
eff 7-1-14
Env-Sw
1301.02 Applicability. The rules in this chapter shall apply to:
(a)
Unlined municipal solid waste landfills, owned by New Hampshire
municipalities and closed after July 1, 1984; and
(b)
Municipal incinerators identified in RSA 149-M:42, IV.
Source. #6095, eff 9-26-95;
ss by #7492, eff 5-18-01;
(See Revision Note at chapter heading for Env-Sw
1300); ss by #8459, eff 10-28-05 (formerly Env-Wm 3001.02); ss by #10599,
eff 7-1-14
PART
Env-Sw 1302
COSTS ELIGIBLE FOR REIMBURSEMENT
Env-Sw
1302.01 Purpose. The rules in this part specify the criteria
by which the department determines whether costs incurred by a municipality to
close a facility identified in Env-Sw 1301.02 are
costs eligible for a 20 % reimbursement through issuance of a grant.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3002.01); ss by #10599, eff 7-1-14
Env-Sw
1302.02 Eligible Costs. A cost of facility closure shall be eligible
for a 20% reimbursement through issuance of a grant, provided that:
(a)
The cost meets the provisions of RSA 149-M:42, III;
(b)
The municipality has paid the cost using funds raised by the
municipality through taxation or loans approved by the voting members of the
municipality; and
(c)
The costs are not covered by other funds such as identified in Env-Sw 1303.02(h) or Env-Sw
1304.02(h).
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3002.02); ss by #10599, eff 7-1-14
PART
Env-Sw 1303
APPLICATIONS FOR LANDFILL CLOSURE GRANTS
Env-Sw
1303.01 Applicability. The rules in this part shall apply to a
municipality that has completed, or is in the process of completing, closure of
a landfill identified in Env-Sw 1301.02(a) and is
seeking to be reimbursed for related eligible costs as specified by Env-Sw 1302.02.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3003.01); ss by #10599, eff 7-1-14
Env-Sw
1303.02 Grant Applications. A municipality seeking to be reimbursed for
landfill closure costs shall submit a grant application that contains the
following information:
(a)
Name, mailing address, and telephone number of the grant applicant;
(b)
Name and location of the landfill for which the grant award is being
requested;
(c)
Landfill permit number, issued pursuant to RSA 149-M;
(d)
Groundwater release detection or groundwater management permit number,
issued pursuant to RSA 485-C;
(e)
A photocopy of the warrant article, corporate resolution, or other
legally binding document authorizing the municipality to undertake the closure
project;
(f)
Closure project information, including:
(1) Name of engineering consultant;
(2) Name of construction contractor;
(3) Bid advertisement date;
(4) Contract award date; and
(5) Construction start date;
(g)
A schedule of the closure costs for which 20% reimbursement is being
requested, with related supporting documentation necessary to substantiate that
the costs are eligible costs as specified in Env-Sw
1302.02, including:
(1) Copies of all related authorized contracts,
change orders, and amendments thereto;
(2) Copies of all related invoices; and
(3) Proof of payment;
(h)
Eligible cost financing information, including:
(1) Total eligible costs paid in cash;
(2) Total eligible costs paid through financing;
(3) Copies of the related institution-generated
finance schedules; and
(4) Monies
received from third party sources and used to close the landfill, other than
benevolent gifts received from third party sources having no liability for
closure costs, including but not limited to funds from the following sources:
a. U.S. Farmers Home Administration or successor
agency;
b.
c.
d. Community development block grants;
e. Potentially responsible party groups formed
to collectively participate in the closure of the landfill; and
f. Insurance policy proceeds;
(i) If closure construction is complete,
certification of completion by a qualified professional engineer and acceptance
of the closure project by the municipality pursuant to Env-Sw
1104.07(f);
(j)
If closure construction is not complete, the estimated future eligible
closure costs and related financing obligations; and
(k)
A notarized statement, signed by a duly authorized representative for
the applicant, affirming that:
(1) The applicant meets the requirements
specified in RSA 149-M:46; and
(2) The material and information submitted is
correct and complete to the best of the applicant’s knowledge and belief.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3003.02); ss by #10599, eff 7-1-14
PART
Env-Sw 1304
APPLICATIONS FOR INCINERATOR CLOSURE GRANTS
Env-Sw
1304.01 Applicability. The rules in this part shall apply to a
municipality that has completed closure of an incinerator identified in Env-Sw 1301.02(b) and is seeking to be reimbursed for
related eligible costs as specified by Env-Sw
1302.02.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3004.01); ss by #10599, eff 7-1-14
Env-Sw
1304.02 Grant Applications. A municipality seeking to be reimbursed for
incinerator closure costs shall submit a grant application that contains the
following information:
(a)
Name, mailing address, and telephone number of the grant applicant;
(b)
Name and location of the incinerator for which the grant award is being
requested;
(c)
Incinerator permit number, issued pursuant to RSA 149-M;
(d)
Groundwater release detection or groundwater management permit number if
applicable, issued pursuant to RSA 485-C;
(e)
A photocopy of the warrant article, corporate resolution, or other
legally binding document authorizing the municipality to undertake the closure
project;
(f)
Closure project information, including:
(1) Name of engineering consultant;
(2) Name of construction contractor;
(3) Bid advertisement date;
(4) Contract award date;
(5) Construction start date; and
(6) Construction completion date;
(g)
A schedule of the closure costs for which 20% reimbursement is being
requested, with related supporting documentation to substantiate that the costs
are eligible costs as specified in Env-Sw 1302.02,
including:
(1) Copies of all related authorized contracts,
change orders, and amendments thereto;
(2) Copies of all related invoices; and
(3) Proof of payment;
(h)
Eligible cost financing information, including:
(1) Total eligible costs paid in cash;
(2) Total eligible costs paid through financing;
(3) Copies of the related institution-generated
finance schedules; and
(4) Monies received from third party sources and
used to close the incinerator, other than benevolent gifts received from third
party sources having no liability for closure costs, including but not limited
to funds from the following sources:
a. U.S. Farmers Home Administration or successor
agency;
b.
c.
d. Community development block grant;
e. Potentially responsible party groups formed to
collectively participate in the closure of the incinerator; and
f. Insurance policy proceeds;
(i) Certification of completion by a qualified
professional engineer and acceptance of the closure project by the municipality
pursuant to Env-Sw 1104.07(f); and
(j)
A notarized statement, signed by a duly authorized representative for
the applicant, affirming that:
(1) The applicant meets the requirements
specified in RSA 149-M:46; and
(2) The material and information submitted is
correct and complete to the best of the applicant's knowledge and belief.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3004.02); ss by #10599, eff 7-1-14
PART
Env-Sw 1305
APPLICATION FILING AND PROCESSING
Env-Sw
1305.01 Purpose. The rules in this part specify requirements
for filing and processing a grant application.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3005.01); ss by #10599, eff 7-1-14
Env-Sw
1305.02 Application Filing. A grant application shall be submitted to the
department, in writing, by the applicant on forms provided by the department.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3005.02); ss by #10599, eff 7-1-14
Env-Sw
1305.03 Application Processing. The department shall process an application
in accordance with RSA 541-A:29.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3005.03); ss by #10599, eff 7-1-14
Env-Sw
1305.04 Application Decision.
(a)
A grant application shall be approved if the application is complete
pursuant to the provisions of Env-Sw 1303 and Env-Sw 1304.
(b)
A municipality having an approved grant application shall be eligible to
receive a grant.
(c)
Grants, not to exceed 20% of the eligible costs associated with an
approved application, shall be awarded and disbursed as specified in Env-Sw 1306 and Env-Sw 1307.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3005.04); ss by #10599, eff 7-1-14
PART
Env-Sw 1306
GRANT AWARDS
Env-Sw
1306.01 Purpose. The rules in this part specify the criteria
by which a grant shall be awarded to a municipality that has an approved grant
application as specified in Env-Sw 1303 and Env-Sw 1304.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3006.01); ss by #10599, eff 7-1-14
Env-Sw
1306.02 Grant Priorities. A grant shall be awarded in a manner
consistent with the priorities established in RSA 149-M:47 and RSA 149-M:49.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3006.02); ss by #10599, eff 7-1-14
Env-Sw
1306.03 Grant Funding. A grant shall be awarded based on funding
pursuant to RSA 149-M:50.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3006.03); ss by #10599, eff 7-1-14
PART
Env-Sw 1307
DISBURSEMENT OF GRANT AWARDS
Env-Sw
1307.01 Purpose. The rules in this part specify how the
department disburses grant monies to a municipality following the award of a
grant.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3007.01); ss by #10599, eff 7-1-14
Env-Sw
1307.02 Financed Eligible Costs. Subject to Env-Sw
1307.04, grant awards for eligible costs that the municipality has paid through
financing shall:
(a)
Be paid by the department on a schedule that corresponds to the
municipality’s payback schedule;
(b)
Include 20% of the principal payment associated with the eligible costs;
and
(c)
Include 20% of the debt service payment associated with the eligible
costs.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3005.02); ss by #10599, eff 7-1-14
Env-Sw
1307.03 Eligible Costs Paid with Cash. Subject to Env-Sw
1307.04 and Env-Sw 1308.03, grant awards for eligible
costs that the municipality has paid with cash shall:
(a)
Be paid by the department as a single payment following grant approval;
and
(b)
Not exceed 20% of the eligible costs.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3007.03); ss by #10599, eff 7-1-14
Env-Sw
1307.04 Failure to Comply. Failure to comply with RSA 149-M:46 shall
result in loss of grant payment.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3007.04); ss by #10599, eff 7-1-14
PART
Env-Sw 1308
ADJUSTMENTS TO GRANT AWARDS
Env-Sw
1308.01 Purpose. The rules in this part specify how the department
adjusts the value of a municipality’s grant award following the municipality’s
receipt or expenditure of funds for facility closure not previously identified
in the grant application.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3008.01); ss by #10599, eff 7-1-14
Env-Sw
1308.02 Adjustments Due to Receipt of
New Third Party Funds.
(a)
The department shall adjust future financed grant award payments to
reflect the receipt of additional funds by a municipality from third party
sources relating to the closure project other than benevolent gifts received
from third party sources having no liability for closure costs.
(b)
For grant awards previously paid in a lump sum, or financed grant awards
for which all amortized grant payments have been made, the municipality shall reimburse the state
for the amount of excess grant money
received as a result of receiving additional funds from a third party relating
to the closure project.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3008.02); ss by #10599, eff 7-1-14
Env-Sw
1308.03 Adjustments Due to New
Expenditures.
(a)
A municipality seeking to be reimbursed for the expenditure of funds for
facility closure not previously disclosed in a grant application shall:
(1) File a landfill closure grant application for
the additional landfill expenditures as specified in Env-Sw
1303; or
(2) File an incinerator closure grant application
for the additional incinerator expenditures as specified in Env-Sw
1304.
(b)
The application shall be processed in accordance with Env-Sw 1305 and Env-Sw 1306.
(c)
The department shall adjust future financed grant award payments to
reflect the expenditure of additional funds by a municipality for eligible
costs relating to the closure project.
(d)
The department shall adjust grant awards previously paid in a lump sum,
or financed grant awards for which all amortized grant payments have been made,
by reimbursing the municipality in a lump sum any shortage of grant award money
due.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3008.03); ss by #10599, eff 7-1-14
Env-Sw
1308.04 Notification of Receipt of
Additional Funds.
(a)
A municipality which received a grant award paid in a lump sum, or a
grant award for which all amortized grant payments have been made, shall notify
the department within 30 days following the receipt or expenditure of funds for
facility closure not previously disclosed to the department.
(b)
A municipality scheduled to receive future financed grant award payments
shall disclose to the department within 30 days of a scheduled grant payment,
whether the municipality has received or expended additional funds for facility
closure not previously disclosed to the department.
Source. #7492, eff 5-18-01; (See Revision Note at
chapter heading for Env-Sw 1300); ss
by #8459, eff 10-28-05 (formerly Env-Wm 3008.01); ss by #10599, eff 7-1-14
Appendix
Rule |
State Statute(s) Implemented |
|
|
Env-Sw 1300 |
RSA 149-M:6, IX;
RSA 149-M:7, XII; RSA 149-M:41-50 |
|
|